About this calculator
Line balancing divides the tasks of an assembly job between workstations so that each station has about the same amount of work, and none has more than the time available per unit (the cycle time set by required output). A well-balanced line needs fewer stations and wastes less idle time. Enter your tasks, their times and which tasks must be done first. You can let the calculator assign stations with a standard heuristic, or enter your own assignment and check it.
Formula
Assign tasks for me
Required cycle time C = Available time ÷ Required output
Minimum stations = ⌈ Σt ÷ C ⌉ Efficiency = Σt ÷ (N × C)
Idle time = N × C − Σt Balance delay = 1 − Efficiency
Σt = total work content (sum of task times), N = stations used, ⌈ ⌉ = round up. Largest-candidate rule: open a station; repeatedly add the longest task whose predecessors are already assigned and which still fits in the remaining time; when nothing fits, open the next station.
I assign the stations
Same formulas, using your station numbers. Each station load (sum of its task times) is compared with the cycle time, and every task’s predecessors must be in the same or an earlier station.
Worked example
Available time 450 min per shift, required output 900 units. Seven tasks (seconds): 1 = 12; 2 = 15 after 1; 3 = 8 after 1; 4 = 20 after 2; 5 = 10 after 3; 6 = 18 after 4 and 5; 7 = 7 after 6.
- Cycle time = 27 000 s ÷ 900 = 30 s
- Work content = 12 + 15 + 8 + 20 + 10 + 18 + 7 = 90 s → minimum stations = ⌈90 ÷ 30⌉ = 3
- Largest-candidate rule: S1 = tasks 1, 2 (27 s) · S2 = tasks 3, 4 (28 s) · S3 = tasks 5, 6 (28 s) · S4 = task 7 (7 s) → 4 stations
- Efficiency = 90 ÷ (4 × 30) = 75%; idle time = 120 − 90 = 30 s; balance delay = 25%
Three stations would need loads of exactly 30 s each, which the task sizes and order do not allow — so here the theoretical minimum cannot be reached.
Assumptions and limitations
- One product, one worker per station, and task times that are fixed averages (no variation).
- Automatic assignment uses the largest-candidate rule, a well-known heuristic. It respects task order but does not search every possible assignment, so a better balance may exist.
- Tasks longer than the cycle time cannot fit in any single station; in automatic mode they are rejected with an explanation.
- Zoning limits (tasks that must or must not share a station), walking time and learning effects are not included.
References
- Groover, Automation, Production Systems, and Computer-Integrated Manufacturing — line balancing and the largest-candidate rule.