About this calculator
Takt time is the rhythm of production set by the customer. It is the available working time divided by the number of units the customer needs in that time. Takt time is not how fast you can work (that is cycle time) — it is how fast you need to work. It is the starting point for line balancing and staffing decisions in lean manufacturing.
Formula
Takt time = Available production time ÷ Customer demand
Available time per day = (Shift length − Planned breaks) × Shifts per day
Worked example
One 8-hour shift with 60 minutes of breaks; the customer needs 420 units per day.
- Available time = (480 − 60) × 1 = 420 min = 25,200 s
- Takt time = 25,200 ÷ 420 = 60 s per unit
- Required rate = 420 ÷ 7 h = 60 units per hour
Assumptions and limitations
- Demand and available time must cover the same period (here, one day).
- Takt time does not allow for unplanned downtime or scrap. In practice, plan your cycle times somewhat below takt time.
- Only subtract planned non-working time. Do not subtract breakdowns — they are a loss to be reduced, not part of the plan.
References
- Lean manufacturing practice (Toyota Production System): takt time = available time ÷ customer demand.