About this calculator
Overall Equipment Effectiveness (OEE) measures how much of the planned production time is truly productive. It multiplies three losses: availability (time lost to stops), performance (running slower than the ideal speed) and quality (parts that are not good first time). OEE is a key measure in Total Productive Maintenance (TPM) and lean manufacturing.
Formula
OEE = A × P × Q
- Run time = Planned production time − Downtime
- A = Run time ÷ Planned production time
- P = (Ideal cycle time × Total count) ÷ Run time
- Q = Good count ÷ Total count
A useful check: OEE also equals (Good count × Ideal cycle time) ÷ Planned production time.
Worked example
A shift has 420 min of planned production time and 47 min of unplanned stops. The ideal cycle time is 1.0 s. The machine made 19,271 parts, of which 18,848 were good.
- Run time = 420 − 47 = 373 min = 22,380 s
- Availability = 373 ÷ 420 = 88.81%
- Performance = (1.0 × 19,271) ÷ 22,380 = 86.11%
- Quality = 18,848 ÷ 19,271 = 97.81%
- OEE = 0.8881 × 0.8611 × 0.9781 = 74.79%
Check: (18,848 × 1.0 s) ÷ 25,200 s = 74.79% ✓
Assumptions and limitations
- Planned production time excludes planned stops (breaks, planned maintenance, no-demand periods), following the common OEE definition. Some companies define it differently — use your company’s definition consistently.
- All times and counts must cover the same period and the same machine or line.
- The ideal cycle time should be the theoretical best, not the average. A performance above 100% means the ideal cycle time is set too long.
References
- Nakajima, S. (1988). Introduction to TPM: Total Productive Maintenance. Productivity Press — origin of the OEE measure.