About this calculator
The reorder point is the stock level at which you should place a new order, so that the delivery arrives before you run out. It is the demand expected during the lead time plus a safety stock that protects against busier-than-usual days. Enter a safety stock you already use, or let the calculator size it from a target service level.
Formula
I know my safety stock
ROP = d × L + SS
d = average daily demand, L = lead time (days), SS = safety stock.
From a service level
SS = z × σd × √L ROP = d × L + SS
σd = standard deviation of daily demand, z = standard normal value for the service level (95% → 1.645, 99% → 2.326).
Worked example
Daily demand 20 units, lead time 9 days.
- Fixed safety stock of 30: ROP = 20 × 9 + 30 = 210 units.
- Service level 95% with σ = 4 units/day: SS = 1.645 × 4 × √9 = 1.645 × 12 = 19.7 units, so ROP = 180 + 19.7 = 199.7 → 200 units.
Assumptions and limitations
- Service-level mode assumes daily demand varies randomly and roughly follows a normal distribution, and that lead time is constant.
- If lead time also varies, more safety stock is needed than this formula gives.
- Service level here is the cycle service level: the probability of no stock-out during a replenishment cycle.
References
- Standard reorder-point and safety-stock model, as in operations-management texts (e.g. Heizer & Render; Silver, Pyke & Thomas).